Hawthorne Elementary
Measure C work has commenced. New portable classrooms were added to assist with providing extra space for classrooms as construction occurs; these rooms will end up being child care spaces after work is completed.
At Hawthorne, the entire campus is being modernized. The main classroom building is currently under construction. It is being renovated in four phases, as there is not enough space or extra rooms on campus to accommodate very many classrooms being modernized at the same time. Over the summer the main building was modernized, getting a complete makeover of the outside, along with new Heating Ventilation and Air Conditioning (HVAC), three modernized kindergarten classrooms with restrooms, new staff room, and a new campuswide fire alarm.
Current work includes: new ADA ramp and stairs at the front of campus, modernization of the classrooms, sewer line, and restrooms in the main classroom building, and a new walkway from the upper campus to the lunch area. The modernization of the classroom building will be completed in phases with a current expected completion date of Winter 2026.
The final phase of work will include the MPR and kitchen remodel.